How to connect electricity to a house and a plot: where to go, what you need and how much it costs

Connecting electricity to a house or plot can take a long time - at least a month and a half, maximum - up to two years. Although you must legally obtain permission within 30 days from the date of application. The very connection of a site or a house to the power grid usually takes up to six months, although it can be connected in a week and a half, or it can take several years. It all depends on the situation, and partly on your persistence.

How to get permission to connect electricity

The procedure is the same, whether you want to connect a plot of land without a building or a permanent (private house) or temporary residence (cottage). First, find the address of the energy sales company in your area. It is easier to do this on the Internet by writing “the address of the energy sales campaign” in the search box and adding the name of the district. There are situations when the site is located on the border of the service areas of two energy sales organizations. Then the application is submitted to the one whose post is closer.

It is possible to bring light to a private house or to a plot if technical conditions are available.You can find out this in the energy supply organization in your area.

It is possible to bring light to a private house or to a plot if technical conditions are available. You can find out this in the energy supply organization in your area.

A completed application and a package of documents are sent to the found address. In each district, the list of documents may differ slightly, but mainly you will need:

  • Application for connection (one of the forms and a sample of filling are shown in the photo below).
  • A photocopy of the passport, the details of which are indicated in the application.
  • A copy of the certificate of ownership.
  • A photocopy of the TIN.
  • A list of all energy-consuming devices that will be connected to the network, indicating their capacity.
  • Load calculation.
  • Plan of the site and the house on a scale, on which to indicate the location of the nearest power supply poles. If there are pipelines on or near the site (gas, water supply, sewerage, etc.), they must be on the plan. On the plan of the house, indicate the places where electrical installations will be installed.

You can submit documents by mail or in person. If you decide to bring the application in person, go to the reception to the secretary, submit the completed application for connection in duplicate with all the documents, on the second (it will remain for you) ask to put the date of acceptance of the documents. With this method of filing, you will be answered exactly within the 30 days prescribed by law.

An example of a completed application for connecting electricity to the site

An example of a completed application for connecting electricity to the site

You can send an application by mail. In this case, you need to wait about 45 days, taking into account the time for mail delivery. If there is no answer, send the request again or go and submit in person. This does not happen often, but there are also such situations: the letter was lost somewhere, sorted, etc.

The photo shows an example of a completed application. This is just one sample, the forms change at least once or twice a year, so you will need to find the currently valid form and fill it out.

What will be in response

In a letter from Energosbyt, you will receive two copies of the agreement on connection to the power grid, signed by the representatives of the campaign, and the “Technical conditions for connection” (TU).

You need to carefully read what was sent to you, if everything suits you, sign the contract and send one copy back.

Read it carefully before signing the contract

Read it carefully before signing the contract

The contract stipulates the term for supplying electricity to the site. The standard cost is 6 months. This is the maximum period allotted by law for the performance of all work. In fact, the connection period strongly depends on how far the pole is from the site.For urban conditions, "near" means at a distance of no more than 300 meters, for rural areas - less than 500 meters.

If the distance is within these limits, you can be connected faster - in a couple of months. If it is far away, the term can be much longer than six months. Although after this period, you can make a claim. Regardless of when you connect electricity to the site, start construction when it is convenient for you.

Sometimes the agreement is vague, without a date. For example, this: "Connection of site No. ... will be made within 6 months, but subject to modernization or repair (construction) of a step-down transformer substation." Having signed an agreement containing approximately the same or a similar text, you can wait for years: until the organization starts construction or modernization of the substation. Only after that your site can be connected to the mains within 6 months.

How much does it cost to conduct electricity

According to the Resolution No. 129 adopted in 2011, if the power consumption is up to 15 kW, and the distance from the site to the nearest pole is 300 and 500 meters (depending on the type of settlement), the cost of connecting electricity will be 550 rubles.

If the load or distance is greater, the connection is at commercial rates, and these are completely different amounts. For example, in Moscow and adjacent regions, you need to pay from 10 thousand rubles for connecting 1 kW of power. That is, if you need 16 kW, then this is 160-200 tr. and more. According to commercial tariffs, connection fees are also considered if the distance to the pole in rural areas exceeds 500 meters, and in urban areas - 300 meters.

How much it costs to conduct electricity depends on the distance to the nearest pole and the required power

How much it costs to conduct electricity depends on the distance to the nearest pole and the required power

Therefore, it is advisable to find out where the nearest connected power pole is located before buying a plot. It depends on how much money is required to connect electricity to the house or plot. Agree, 550 rubles and hundreds of thousands - the difference is more than tangible.

Sometimes, even if you need 15 kW and the pole is within the specified limits, you are told that some work must be paid separately. No one has the right to demand payment from you. Even if an increase in equipment capacity or a network upgrade is required. If your requests fit into the conditions stipulated above, the cost of connecting electricity to a land plot or house will be 550 rubles.

What then

After the permission and technical conditions are received, it is necessary to develop a project for the electrification of the site. Basically, you can draw up a wiring plan for the house yourself, but if the house is large, with utility and technical rooms, with electricity supply to the installation area of ​​a pumping station or a pump for water supply, it is better to order a project from a specialized organization. And the best option is in the energy sales organization where you applied for connection. There will be much less problems with acceptance.

Example of a home electrification project

Example of a home electrification project

If you draw up the project yourself, it will need to be coordinated with the power supply organization. If the requirements are met, it will be approved for you, if there are violations, they will indicate what needs to be changed. After making the changes, submit the project for signature again. Only having in hand a ready signed project, you can start implementing it.

Similar posts
Comments 72
  1. Diana
    10/02/2017 at 13:27 - Reply

    Good day! We bought a plot, before that there was one, then a neighbor divided it into 2 parts. Column 15 kW 1 for two with a neighbor, of course this power is not enough for two. So the chairperson suggested installing her own pillar for 115,000 (not officially) or 225,000 (officially). Tell me, are the amounts generally adequate? Are the actions lawful?

    • Evgen
      10/05/2017 at 11:50 - Reply

      the amounts are clearly inadequate.

  2. natalia
    10/15/2017 at 10:00 - Reply

    good afternoon, but how much can a project cost and the term of its preparation?

    • A
      04/21/2018 at 18:13 - Reply

      Average 20,000

  3. Elena
    10/27/2017 at 15:07 - Reply

    Good day! Today I had an emergency, the cable leading to the pole sparkled and there was a wire break. In case of calling the emergency service, how much will it cost to eliminate the accident in Kursk. Thank you.

    • Administrator
      10/28/2017 at 20:49 - Reply

      We sympathize. Your local service can answer your question. Rates differ in different regions.

      • Igor
        04/04/2019 at 13:53 - Reply

        Good day. Tell me please. I have two plots in the village of 12 and 8 acres. They are adjacent. But according to the documents, they are different and delimited. I want to spend 8 acres of electricity. The site is bordered by SNT and there are pillars. And 12 acres are just located along the power line of the village. If by footage, then from the village. Village pillar - 120 meters. How to apply correctly so as not to get money. And how much can it cost me? After all, they won't connect me from the pillars of SNT? thanks in advance

  4. Vladimir
    02.11.2017 at 19:10 - Reply

    Good afternoon, tell me what to do if the nearest connected line is 206 meters, and the power supply company offers to bring it from a more distant line, naturally at my expense, the contract does not say anything for what the money will be taken for, I have not signed the contract yet, I took it for consideration ... Thank you.

    • Administrator
      04.11.2017 at 10:26 - Reply

      Maybe there is no technical opportunity to stretch from the nearest line. It happens. Try to talk to the designer about this. May I help.

  5. Peter
    01/22/2018 at 00:01 - Reply

    Tell me what to do. Village Ivanisovo, Pereslavl region. The house on our street was once connected to the power grid of Vityaz LLC, which was connected through its own transformer to Yarenergo - but this “knight” is dead, the transformer is still working, but our house has been disconnected from E / E. We wrote to Yar energo to connect to them and were refused, they say the house was once connected. What now?! And we have about 10 such houses.

    • Administrator
      01/22/2018 at 00:16 - Reply

      You need to resolve the issue in local authorities. If the refusal is written, go to an appointment with your boss with it. If there is a technical possibility, you should not be denied ...

  6. Anita
    25.01.2018 at 08:42 - Reply

    Good day! Can I apply for electricity connection now in winter? To the site? You need to install a post. What is needed for this? And how much will that cost?

    • Evgeniy
      26.01.2018 at 18:37 - Reply

      There is a month left until spring, so it's time to make inquiries. To submit an application, you must contact the network organization that serves the power grids in the area where your site is located.
      You can find out the cost only "locally". In the meantime, you need to decide which cable is advisable to start - two-core (220 V) or three-core (380 V). Naturally, in the second case it will be more expensive, because it will be necessary to install a 3-phase meter and an RCD, lead a four-core SIP to the site.

  7. Olga
    02/01/2018 at 17:52 - Reply

    Hello. Please tell me what to do next and how to write a letter on the power grid so that the "movement" has already started. In 2016, they submitted an application for joining, in the 3rd quarter of 2017 there was consideration. The contract was not given, they say to wait for their turn.

    • Vasiliy
      02/28/2018 at 12:10 - Reply

      As for me, you should always ask to justify the refusal in writing. With such a piece of paper in hand, it will already be possible to drop in at the reception at the local administration.

  8. Rauf
    02/14/2018 at 22:33 - Reply

    Good time! I want to buy an Izhs plot, there is light on the border of the plot, but the chairman asks for 200 tons of connection. Is it possible to bypass it and connect on my own? Thank you!

    • Vasiliy
      02/17/2018 at 12:01 - Reply

      Is the site on municipal land? If on a municipal one, then there is an opportunity to join the state program for connecting to utilities.
      Who owns the electrical networks passing by the site? Have you contacted the owner of the networks?

    • Sergei
      28.02.2018 at 12:33 - Reply

      In all such cases, it is necessary to bypass intermediaries. I read about a case in Obninsk, where, instead of 550 rubles, a local krokhobor asked for 300 thousand! And as you find out the prices for connecting to communications in the Moscow region, you are generally amazed.
      A few words about bypassing intermediaries from personal experience - it concerns gas, but does not change the essence of the matter. In 2014 he decided to supply gas to the bathhouse. I asked around my acquaintances and found out that a local idle entrepreneur named Yura takes about 25 rubles for such work. I turned to the gas section and they announced to me the amount within 10 thousand rubles! To be honest, I was quite surprised by this difference. In fact, I paid them 8,300 rubles - this included work, 23 meters of pipe, two cranes and one stand.

  9. Elena
    02/25/2018 at 13:53 - Reply

    Hello! Tell me, on a site from the state for large families, electricity poles are carried out at whose expense?

    • Evgeniy
      02/28/2018 at 11:38 - Reply

      Based on my modest experience, I will assume that everything depends on the local administration. At one time, it was built according to the "Rural House" program - it was financed both from the state and from the regional budget. The poles were installed by local power grids. Connection documents were drawn up at their own expense.
      As for the physical connection, then how lucky is anyone. Nobody paid for the work, but someone paid for the material (self-supporting insulated wire and suspensions), and some did not. Those. local electricians said that now, for example, there is no self-supporting insulated wire - buy and we will connect. Personally, I paid only for suspensions, someone for suspensions and self-supporting insulated wires, and someone was lucky and he got the material for free.
      What do they say to you in the administration on the territory of which the land plot is located?

  10. Misha
    03.03.2018 at 18:04 - Reply

    Hello! Previously, we fed from a kfkh (peasant farm), we paid him and he supplied the company with electricity. Now he abandoned the transformer, we have meters, but the power grids cut the wires to all 15 clients and said that the kfkh has a debt. Please tell me what to do. And even they say they drew up the act without us.

    • Sergei
      03/07/2018 at 15:12 - Reply

      Well, after all, the owner of the power grids cut off. What do they advise you to do?

  11. Vladimir
    03/16/2018 at 13:51 - Reply

    Hello!
    If the site is jointly owned by 2 owners, is it possible to connect 30 kW to the site (house) by submitting two applications from each owner, 550 rubles each?
    Thank you.

  12. Catherine
    28.03.2018 at 08:48 - Reply

    Good time. The situation is such an overhead line is laid from the post along the brick wall of the neighbor's fence. It needs to be redone according to the rules. But the problem is that the line itself is 70 meters long and there is no possibility to install the poles. since the width of the entrance is 1 meter, neither a drill machine nor a crane will pass. How can you run a cable at a lower cost?

    • Nikolay
      03/29/2018 at 11:17 - Reply

      If I understand correctly, you are not considering laying the cable in the ground?
      As for the pole, since there is no way to use heavy equipment, then the option remains to do everything manually. Dig a hole, pull up a post and install using guy ropes. The problem is that it will take about 10 people to install the pole.

  13. Novel
    04/02/2018 at 05:05 - Reply

    Good day!
    An agreement has been concluded with a grid organization for technological connection to power grids. Plot of private household plots, in the village, pillars nearby There are no buildings on the site, there is also no fence yet, the boundaries of the site are taken out. The term for joining has already passed, and a letter has come from the network organization with the following content: “Dear applicant! At your request IDGC of Siberia is ready to carry out the actual connection. If you are ready, you must send a notification to our address about the fulfillment of your part of the technical conditions. "
    The contract specifies that the Applicant (that is, I) must fulfill the obligations to carry out technological connection measures within the boundaries of the site on which the connected power receivers specified in the technical specifications are located.
    Tell me, what activities should I perform within the boundaries of the site, if there are no buildings on it?
    Thank you in advance!

    • Evgeniy
      04/02/2018 at 12:18 - Reply

      It turns out that you don't even have technical specifications on hand? How then are you going to implement them? What I personally saw when connecting the sections - a pole is installed on the site, and not a shield with metering and protection devices is attached to it. Those. without the same electricity meter, no one will obviously connect you.
      In order not to rack your brains again, call the toll-free number 8-800-1000-380 (IDGC of Siberia).

  14. Lika
    04/09/2018 at 10:43 - Reply

    Hello, if 10 years ago we had both electricity and water, gas then my mother was driving and now the light is turned off, you need to pull a new line how much will it cost in the Rostov region.

  15. Maxim
    04/17/2018 at 10:46 - Reply

    Hello. There is a plot in the suburbs. Of the buildings, only a change house with internal electrical wiring. The nearest post is located 70 meters from the change house. And there is a pillar below the level of the change house. Pole installation is not possible. It was suggested to install pipes. Moesk refused to do this. Like, install everything, and then we'll connect it. Even for money. Now we are racking our brains where to get two five-meter pipes.

  16. A
    04/21/2018 at 18:10 - Reply

    Post installation cost 15000 including post purchase. You are being fooled.

  17. Tatyana
    04/25/2018 at 15:11 - Reply

    Hello! Tell me if it is possible to supply electricity to the land for rent (private household plots for agricultural purposes, field)

    • Vasiliy
      04/26/2018 at 12:39 pm - Reply

      It is written that the connection requires ownership or other legal basis. As I understand it, in your case, this is a lease.

  18. Oksana
    04/25/2018 at 22:36 - Reply

    Hello. The fact is that we have a narrow and long section and on the one hand we get Ratanin Street, and on the other Lenin Street. The house and plot are registered on Ratanin street, but there is a house on the Lenin side. And it turns out that we have already collected all the documents and sent them for registration, but the contract has not yet been signed. And an engineer from our area called us and said that they would guide us the light from the side of Ratanin Street to the site, and along the site to the house (this is about 90m) we are on our own, but we said that we didn’t like it and we didn’t need pillars all over the site and that the house is located on the Lenin side means and drive from the Lenin side, there is less than a hundred meters to the nearest pillar. Please tell me how we should be in this situation. Thank you.

  19. Love
    05/12/2018 at 10:07 - Reply

    if an electrician came and found that I was using electricity in accordance with the act for those services but without the act of connection and drew up an act as illegal connection to the network and brought the case to court without any initial warnings, even without the owner of the house. Does he have the right to act this way?

    • Administrator
      12.05.2018 at 10:22 - Reply

      It has.

  20. Alexei
    05/25/2018 at 21:36 - Reply

    Good evening. Please tell me !!! No where there is no information !!! I have IZHS. Can I install a concrete support outside the border of my plot, and in front of it? Do you need any approvals for its installation?

    • Administrator
      28.05.2018 at 21:27 - Reply

      You must have an electrification project. There it is precisely indicated in what place to put the post. And in general, the pillars should be on the "common" land, and not on the site.

  21. Maria
    04.06.2018 at 14:29 - Reply

    Good day, Tell me how to be. In the 90s, the site was connected to electricity in SNT. After a while, the post expired and the section was turned off. Due to the lack of need for electricity, no one was involved in the renewal.Now the chairman demands 50,000 rubles for the connection as from the site, which is connected for the first time, citing the fact that the site has stood without electricity for almost 15 years and SNT has invested a lot over this period and this is like compensation for their investments on my part. But the site has already been connected, does it really have the right to force it to reconnect, and not to resume the connection?

    • Administrator
      04.06.2018 at 16:09 - Reply

      The answer to your question can only be found in the legislative framework. You need to look for regulations that regulate the activities of SNT.

    • Kate
      07/03/2018 at 15:05 - Reply

      these chairmen generally went crazy, they also asked for 100 thousand from us for connection, arguing the same

      • Oksana
        03/12/2019 at 19:14 - Reply

        Can you please tell me if it is true that the state should provide electricity for free up to 25 meters to my site. ?? The nearest pillar is 700 meters, Energosbyt said the resolution is 10 thousand, and work with materials 170

  22. Evgeniy
    06.06.2018 at 00:06 - Reply

    Good afternoon. For the allocated power of 25 kW 380. What cross-section is needed for the cable to be supplied underground from the pole to the house (25m). Aluminum?

  23. Olesya
    06/19/2018 at 01:52 - Reply

    Good evening!!! Please tell me when replacing old wooden poles with new concrete ones, you must reconnect the light, if the light was connected to the old post not from the meter but from the administration….

    • Ludmila
      09/24/2020 at 17:00 - Reply

      Hello, is it possible to apply for the connection of electricity

  24. Alexander
    12.07.2018 at 20:03 - Reply

    Hello, please tell me if 220v is connected and issued, but you need to connect 380v, then you will need to reissue the connection.

    • Administrator
      07/18/2018 at 13:46 - Reply

      Yes, you will have to redo the project, pull another line ... everything will have to be reissued

  25. Maxim
    08/06/2018 at 16:59 - Reply

    Good afternoon, in the city of Volosovo, for connecting to electricity, the company coordinating my single-line diagram project asked for 65,000 rubles for the connection, this money includes work on the installation of a Pillar on my site, assembly and installation of a metering cabinet on a pole on my site and laying a wire from my section to the highway (this is about 100 meters) Taking into account all materials ..
    If I understand correctly, then everything that is done on my site I must either do it myself or ask them to do it by paying for the services.
    1. But do I have to pay for the wire and work on its installation from my site to the power line?
    2. Along the route of the wires to my site, there are two pillars with one problem, and the second, which is closer to my site but stands on the common territory, neighbors claim that they put it at their own expense and prohibit throwing a wire through it. At the same time, alas, I have no other option to connect my site to electricity.

  26. Tatyana
    08/21/2018 at 19:51 - Reply

    A summer cottage with a house (owned) on all sides borders on plots (owned), has a single driveway. According to our application to the power grid company (in August), the connection was made in October for the connection of electricity. And in February, the power grid company installed 2 pillars in the middle of the dumped road (a lot of snow is not visible), as if for us, thus blocking the access to the site. Upon our request to move to the side of the pillars, they refuse, arguing that they were given a corridor. It turns out wherever the pillars are stuck - they are right everywhere. They did not agree with us. And if there is a fire, will fire trucks fly through the air? Where can we go? Are there any violations of the law?

    • Nikolay
      08/22/2018 at 12:04 - Reply

      I didn't understand the phrase “a lot of snow - you can't see”, you can't see what?
      On the installation of supports - it is regulated by the PUE (rules for the installation of electrical installations). Excerpt from clause 2.4.53:

      Intermediate supports must be designed for the following load combinations:

      • ● the simultaneous effect of a transverse wind load on wires, free or covered with ice, and on the structure of the support, as well as loads from the tension of the branch wires to the inputs, free from ice or partially covered with ice (according to 2.4.12);
      • ● on the load from the tension of the branch wires to the inputs, covered with ice, while taking into account the deflection of the support under the load;
      • ● for a conventional design load equal to 1.5 kN, applied to the top of the support and directed along the axis of the overhead line.

      I suspect that in your case, only the option of laying the cable in the ground may be suitable. You can put pressure on electricians through firefighters (Ministry of Emergency Situations), since you mentioned the impossibility of transport access in case of an emergency.

  27. Natalia
    09/27/2018 at 12:03 - Reply

    Hello. We bought a plot. All documents are ready, even the shield is assembled. In September, 6 months come from the signing of the contract. They promise us a post will not be delivered soon and across the street from the site. The question is: who should lead the cable from the pole to the area where the pipe stand is.

    • Nikolay
      09/29/2018 at 10:15 am - Reply

      Logically, the one who puts the pole has the authority to lead the cable from it. This is exactly what happens in our village. The regional center has its own organization, for the rest of the district's settlements - another. Everyone works only in assigned territories and, as far as I know, has no right to connect anything on the territory of another service organization.

  28. Lily of the valley
    09.10.2018 at 16:20 - Reply

    Good day! We want to conduct electrical wiring underground, because to the nearest post more than 25 m, is it necessary to obtain a permit for earthwork and what documents are needed? The connection application was left, the state fee was paid.

  29. Irina
    11/08/2018 at 14:07 - Reply

    Good day! Tell me how to be? We bought a plot of Izhs, but there are no pillars and no light, respectively, at the moment there is an open field. Where to go to put the poles and conduct electricity. Lands were given by the administration for large families. Sredneuralsk, Brick. In 2013 and still there is no clear answer.

    • Evgeniy
      11/08/2018 at 22:30 - Reply

      As I understand it, this is a federal program. If no one wants to move, it's time to contact the prosecutor's office.

  30. Gulmira
    11.12.2018 at 19:07 - Reply

    Good evening. Please tell me how much the connection will cost. They paid 550 rubles for the technological connection. They stretched the wires, installed a counter in a box on a support. Now we are waiting for the wizard, who will check how we did everything, and then sign the documents. Then the CSC will give me the documents with which I will go to Energosbyt to conclude an agreement, and only then they will give an application for connecting my house to the network.

    • Administrator
      11.12.2018 at 19:08 - Reply

      Good evening. Only the local service can answer you, and in relation to your specific case. Call them and ask.

      • Gulmira
        11.12.2018 at 19:12 - Reply

        So you have to pay for connection and for connection too?

  31. Stanislav
    03/17/2019 at 18:22 - Reply

    Good day!

    My site is on the other side of the bay from other sites. The neighboring pillar is about 350 meters in a straight line (across the bay), overland - about 700 meters.

    Tell me how 500 meters are determined for connecting for 550 rubles - by land or in a straight line?

    Thank you.

    • Administrator
      03/17/2019 at 22:08 - Reply

      Depends on local power supply. Most likely, they will count on land.

  32. marina
    04/15/2019 at 11:18 - Reply

    A fire broke out at the site in a summer cottage association. The meter also burned out. What needs to be done to connect the electricity to start building a new home. There is a bathhouse on the site

  33. Alexander
    04/16/2019 at 07:32 - Reply

    In the village, electricity was supplied to the main house, a guest house was built at the end of the plot, the electrician says if a wire is pulled to it, there will be losses. Can an additional pole be installed and connected from it?

    • Sergei
      04/22/2019 at 21:40 - Reply

      It is not entirely clear what size the site is. Really a few hectares? If so, there will certainly be losses. If the guest house is within 10-15 meters, why not use SIP 2x16? With this wire cross-section, the losses will be insignificant.
      About the pole, you can only be told in local power grids.

  34. Olesya
    24.05.2019 at 20:56 - Reply

    Good evening! Please tell me the answer to my question. There is a plot of land in the village with my grandmother (my mother's aunt), which she inherited from her uncle (in 2018, it was registered as property). On this site there is a house built in 1949, which was donated by the same uncle to my grandmother in 1992 (my mother's mother), there is a donation contract for the house and a certificate from the archive in the donation contract indicates the land (29 arable land and 15 for the house and garden). My mother's mother died in 2017, so her sister inherited the land, my mother wants to enter the house. She needs a certificate from the BTI technical plan what is the cost? She wants to join us so that we can lead the light (there was a meter and it was sealed) to the plot (maybe there is an option without entering the house as an inheritance?). And it is necessary to chew the earth in order to conduct the light? Aunt will write down the earth to mom. - what and the cost of work for carrying out the light? The pillar is less than 50 meters from the house. Thanks in advance.

    • Vladimir
      05/29/2019 at 10:27 - Reply

      As far as I know, an application for light is accepted only if there are documents on the property, i.e. The owner of the house and plot must submit They require both a certificate for the house and a certificate for the land.
      As for the BTI, it is unlikely that there is a single tariff throughout the country - you need to call and find out. When you collect all the documents that are at hand, including documents from the BTI, you can look at the MFC - they should know about the whole procedure there. The friend gave everything he needed to the MFC, and then only took the certificate for the house and land (after buying the house).

  35. Anna
    06/01/2019 at 14:42 - Reply

    Good day! Our house is divided into two halves. The house has 2 owners. There is a counter in one half. We would like to conduct the light into our half as it should be (our own meter, contract). They say you need a written permission from the second owner. How is it regulated?

  36. Tosya
    11/14/2019 at 20:59 - Reply

    I designed the light on the site, then they built a house (we use the light but haven’t paid yet) now do we need to issue it to the house? Or is it enough that there is clearance on the site.? The seals are

  37. Ruslan
    12/07/2019 at 15:04 - Reply

    Hello, we bought a plot, built a house, we want to install electricity, everyone went through the contract, everything is fine. The lighting department workers in our area advised us to buy a 2013 meter that had never been used from a store. They bought it well, according to the documents they like everything, but suddenly, at the end, when they should already conduct the light, Someone from the elders did not like the meter, and he decided not to conduct the light, so we have been sitting without light for a couple of months.

    What to do? To sue?

  38. Larissa
    12/21/2019 at 04:07 - Reply

    good day! What to do and how to be !!! There are 2 adjacent summer cottages at 58 and 60 Vishneva St., SNT "Kolyaginskiye Hills" of the Republic of Khakassia. Plot number 60 - 8 acres, (extreme from the main street), elongated and ending on another Abrikosovaya street, is a pine forest, earlier in Soviet times it was planted along the road and played the role of a protective strip. pines planted in 2 rows. I have concluded an agreement for connection to power grids at 60 Vishnevaya Street. At present, IDGC of Siberia requires me to perform technological connections under the agreement, but from the side of Abrikosovaya Street, where the boron ends, threatening that in case of failure, a penalty will be charged ... I wrote to them in writing that in the subject of the contract, the legal address is 60 Vishnevaya Street, not Abrikosovaya Street, to which IDGC of Siberia, referring to legislative acts, claims that they are guided not by the address, but by the cadastral number of the site.The construction of the dacha was planned on an empty adjacent site on 58 Vishneva Street, cutting down 20-year-old pines from the side of Abrikosovaya, in my opinion, is criminal, and the site is narrow, it's just a forest belt. Electricity on Vishneva Street is planned for next year. How to be? Some people advise to connect and then refuse, but this will cost 17 thousand rubles. Remarkably, please help me figure it out !!!

  39. Valentine
    01/30/2020 at 15:17 - Reply

    Tell me please! We have a new town - they promised to build a store over time and everything that is needed in the town - now our senior in the house is tearing and rushing to connect the stall to our 5-storey house temporarily, but the stall is close somewhere 10-15 m from other houses - there and the pillars stand from the UK-and the pillars on the road are also nearby, but these houses that are close they refuse to connect to them to the stall, and our house is further than them. The eldest of our house arranges for everyone to sign up for a connection. Is this correct and what is better for us or should we not connect? Explain to me and to several other residents of my house? This is the city of Tula and Molodezhny

  40. Nikolay
    03/16/2020 at 07:47 - Reply

    Hello. Please tell me. I bought a plot in SONT, but there is no chairman there, just some owners. Nearby, 100 meters away, there is a 6 kV power line. In the mountains of the network I was told to do a project, buy a ktpn, build and install poles according to the project, and then they will connect…. Is it so? Or do they have to do all this?

    • Vasiliy
      03/16/2020 at 18:36 - Reply

      KTPN is a complete outdoor transformer substation !? Your requirements are not feeble. How much will the connection cost?

  41. Svetlana
    03/28/2020 at 06:37 - Reply

    We are concluding our third connection agreement. The two previous companies did not fulfill their obligations. The third company also signed an agreement with us, issued technical specifications, but is in no hurry to connect. You need to put 12 supports. It turned out that the supports to which our line is connected are not registered and the company may not receive money from the state for the construction of our line. We were unambiguously offered to build at our own expense. In this situation, who will be the owner of the line and who will maintain it?